Offshore Wind

How the Biden Administration Has Made Offshore Wind a Priority

Max Meyer, MJLST Staffer

Since coming into office in January of 2021, the Biden Administration has made fighting climate change and reducing domestic greenhouse gas (GHG) emissions a priority. In particular, the Biden Administration set a goal of doubling the nation’s offshore wind capacity in Executive Order 14008. Reaching this goal would result in 30 Gigawatts (GW) of offshore wind capacity. Developing offshore wind energy will help states reach their clean and renewable energy goals as many sates on the coast do not have large wind energy resources on land. Since the issuance of Executive Order 14008, the Department of the Interior (DOI) has taken several steps towards reaching that goal.

Statutory Authority

Under the Outer Continental Shelf Lands Act (OCSLA) (codified at 43 U.S.C. ch. 29), passed in 1953, the Secretary of the Interior is charged with the administration of mineral exploration and development of the Outer Continental Shelf (OCS). The OCS is defined as “all submerged lands lying seaward of state coastal waters (3 miles offshore) which are under U.S. jurisdiction.”

In the Energy Policy Act of 2005 (EPAct), Congress created the OCS Renewable Energy Program to be administered by the DOI. Under this authority, the DOI in 2009 promulgated regulations for leases, easements, and rights-of-way for renewable energy development in the OCS. The Bureau of Ocean Energy Management (BOEM), under the DOI, is the agency tasked with overseeing the renewable energy development program.

Regulatory Authority

The BOEM renewable energy development program is broken into four steps: (1) planning, (2) leasing, (3), site assessment, and (4) construction and operations. During the first step, BOEM identifies Wind Energy Areas (WEAs) which are “locations that appear most suitable for wind energy development.” After WEAs have been identified, BOEM issues a public notice to gauge the interest in leasing land in the WEA. Depending on the interest received from BOEM, leasing is done through either a competitive or noncompetitive leasing process.

After leasing is completed, the lessee must submit a Site Assessment Plan (SAP) to BOEM. The purpose of the SAP is for the lessee to provide documentation so that BOEM can evaluate whether the project will comply with applicable regulations. The agency can either approve, approve with modification, or disapprove the SAP. Finally, the lessee must produce a Construction and Operations Plan (COP). As the name suggests, this submission includes a “detailed plan for the construction and operation of a wind energy project on the lease.” BOEM reviews the COP, including environmental review, and can either approve, approve with modification, or disapprove the COP.

Recent Offshore Wind Developments

In May 2021, the DOI approved the COP for the Vineyard Wind project located near Martha’s Vineyard and Nantucket. This is the first large-scale, offshore wind project in the United States. The project will have 800 Megawatt (MW) of energy capacity which is enough to power 400,000 homes and businesses. Construction of the project began in November 2021. One of the first steps in the construction process will be placing two transmission cables to transmit electricity from the Vineyard Wind project to the mainland.

Also in November 2021, the DOI approved the COP for the South Fork Wind making it the second large-scale, offshore wind project in the United States. This project off the coasts of New York and Rhode Island will have a capacity of 130 MW which is enough to power approximately 70,000 homes.

In addition to granting final approval of several projects, BOEM has also taken action in the earlier steps of the OCS renewable energy process. For the Carolina Long Bay WEA, located off the coast of the Carolinas, the BOEM began taking public comments on a proposed lease. In October, BOEM received the COP for the Mayflower Wind project. This project would also be located near Martha’s Vineyard and Nantucket and would have an energy capacity of more than 2 GW. If approved, the Mayflower Wind project would be one of the largest offshore wind projects in the United States. BOEM also published a Call for Information and Nominations to gauge commercial interest in wind energy development in the Gulf of Mexico.

BOEM has also taken steps to advance offshore wind in the Pacific Ocean in 2021. In July, BOEM published a Call for Information and Nominations to determine commercial interest in the Morro Bay Call Area East and West Extensions, a portion of the Morro Bay WEA. This WEA is located off the coast of Central California. Finally, BOEM designated the Humboldt WEA off the northern coast of California moving closer to the leasing process in this area.

Despite heavy support from the Biden Administration, offshore wind does face opposition. The commercial fishing industry has emerged as a strong opponent of these projects. The industry is concerned that the turbines will impact fish and hinder access to fishing grounds. The Biden Administration could face legal challenges to offshore wind development, particularly under the National Environmental Policy Act (NEPA), from the fishing industry. One such challenge in Fisheries Survival Fund v. Haaland, 858 F. App’x 371 (D.C. Cir. 2021) has proven unsuccessful for the fishing industry.

While the DOI and BOEM have taken many actions to further develop offshore wind in the United States, much more will have to be done to reach the Biden Administration’s goal of 30 MW of offshore wind capacity by 2030. Nonetheless, offshore wind is an important resource for coastal states looking to decarbonize their energy generation and for reaching the Biden Administration’s decarbonization goals.